Projects

Dashboard / Fabricate Steel Structure & Install Piping Process

Fabricate Steel Structure & Install Piping Process

1. Install Gas Pipeline 5" for 50 MW, PLTG Teluk Lembu Pekanbaru (V-Power)
 
2. Install Gas Pipeline 3" for 9 MW, PLTG Teluk Lembu Pekanbaru (V-Power)
 
3. Replacement Pipe Spool Metering PLN, PLTG Teluk Lembu (PT. Hutan Alam)
 
4. Fabrikasi Safety Sign 100 pcs & Warning Sign 200 pcs, PT. WIS - NDD 13 (PT. DP)
 
5. Fabrikasi BCR 64 pcs, PT. WIS - NDD Area 13 (PT. Dayatama Polanusa)
 
6. Fabrikasi SID / Plat Form Quadran 5 & 6 (42.000 kg), PT. WIS - NDD 13 (PT. DP)
 
7. Fabrikasi Shelter & Fire Extunguisher Rack (30 pcs). PT. WIS - NDD 13 (PT. DP)
 
8. Install Gas Pipeline 6" Sch. 80 for 15 MW, PLTG Siberida, Rengat (PT. Hutan Alam)
 
9. Install Gas Pipeline 2" for 15 MW, PLTG Siberida, Rengat (PT. Rovina Jaya Sentosa)
 
10. Demolish & Installation USM Meter 10” PT. PGN – Perawang, Riau (PT. TIS – PT. TGI)